The Mobridge City Council held a special meeting on Monday, July 21st, to approve a change order for an additional 150 tons of material on the trail overlay project. Mobridge City Finance Officer Heather Beck said this summer’s rainfall prompted the change.
Beck said the work will be an in-and-half overlay in most spots, with some low points filled in higher, and a couple places that will be completely cut out and new material put in.
Council passed a motion to approve Change Order #1 on the trail overlay project.