The South Dakota Department of Transportation says that paving work will begin tomorrow (June 21, 2022) on an asphalt resurfacing project on SD Highway 1806, approximately 18 miles southeast of Fort Pierre between mile markers 150 and 164.
Work on the project will include cold milling three quarters of an inch to correct profile of the road and then paving with asphalt concrete. During both operations, traffic will be carried through the work zones with the use of flaggers and a pilot car. Motorists can expect up to 15-minute delays during these times. The contractor anticipates finishing the paving in mid-August and having the project completed by Aug. 26, 2022.
The cold milling will begin approximately Tuesday, June 21, 2022, with the asphalt blade laid material being placed on Thursday, June 23, 2022. The contractor will begin asphalt paving approximately Monday, June 27, 2022, weather permitting.