Milling of streets will begin this afternoon (Aug. 17, 2022) in Fort Pierre. Work will start on Scotty Philip Avenue. It will then move to Wandel Avenue, then to La Framboise Drive and finishing on Park Avenue.
Curb and gutter work will begin tomorrow (Aug. 18, 2022) at 10am CT on Scotty Philip Avenue, then move to Wandel Avenue. Traffic will be routed around the project for access to the Stanley County Fairgrounds.
The alternate route recommended for the contestant entrance at the Fairgrounds is to turn at Park Avenue, proceed to Casey Tibbs Street, then use Wandel Avenue to enter the Fairgrounds.