SEPTEMBER 18, 2024:
BALTIMORE (AP) — The U.S. Justice Department is suing the owner and manager of the cargo ship that caused the Baltimore bridge collapse. The lawsuit filed Wednesday (Sept. 18, 2024) in Maryland seeks to recover more than $100 million that the government spent to clear the underwater debris and reopen the port. The case alleges that the electrical and mechanical systems on the Dali were improperly maintained, causing the ship to veer off course before striking the Francis Scott Key Bridge in March. A spokesperson for Grace Ocean said the owner and manager had no comment at this time, but “look forward to our day in court to set the record straight.”
JUNE 24, 2024:
BALTIMORE (AP) — The cargo ship Dali is headed out of Baltimore for Virginia. It departed Monday morning (June 24, 2024), nearly three months after it lost power and crashed into one of the Francis Scott Key bridge’s supporting columns and caused the bridge to collapse. The 984-foot Dali started moving shortly before 8:30 a.m. with four tugboats. It is headed to Norfolk, Virginia, for the removal of the remaining containers on the vessel and additional repairs. The ship lost power and propulsion shortly after leaving the Port of Baltimore early on March 26 and crashed into one of the bridge’s supporting columns, killing six construction workers.
JUNE 11, 2024:
BALTIMORE (AP) — The main shipping channel into Baltimore’s port has fully reopened to its original depth and width following the March 26, 2024, collapse of the Francis Scott Key Bridge. The channel was blocked to most maritime traffic for several weeks while crews worked to remove an estimated 50,000 tons of steel and concrete from the Patapsco River. On May 20, the wayward cargo ship Dali was refloated and guided back to port. The ship lost power and crashed into the bridge shortly after leaving Baltimore for Sri Lanka. Six members of a roadwork crew were killed in the collapse.
MAY 20, 2024:
BALTIMORE (AP) — The container ship that caused the deadly collapse of Baltimore’s Francis Scott Key Bridge was refloated at high tide Monday (May 20, 2024) and began slowly moving back to port, guided by several tugboats.
The Dali had been grounded at the collapse site for weeks after it lost power and crashed into one of the bridge’s supporting columns on March 26, killing six construction workers and halting most maritime traffic through Baltimore’s busy port.
The ship appeared to start moving shortly after 6 a.m. as crews began maneuvering it out of the wreckage. It started and stopped a few times before slowly backing away from the collapse site.
With the hulking cargo ship removed from the mouth of Baltimore’s harbor, a newly opened void appeared in the city’s skyline. The altered waterscape also highlighted the progress made on the cleanup effort as crews have already removed hundreds of tons of mangled steel from the collapse site.
Officials said the Dali would move at about 1 mph on the roughly 2.5-mile (4-kilometer) trip back to port, a fraction of the speed it was traveling when it lost power and brought down the bridge. Pieces of the bridge’s steel trusses protruded from the ship’s bow, which remained covered in mangled concrete from the collapsed roadway.
Officials have said the Dali will likely remain in the port for a several weeks and undergo temporary repairs before being moved to a shipyard for more substantial repairs.
Crews began preparing the ship to be refloated about 18 hours before it started moving. That process included releasing anchors and pumping out over 1 million gallons of water that were keeping the ship grounded and stable during complex cleanup operations. Crews conducted a controlled demolition on May 13 to break down the largest remaining span of the collapsed bridge, which was draped across the Dali’s bow.
Dive teams also completed inspections of the site to confirm there were no obstructions that would hinder the voyage.
Maryland Gov. Wes Moore, who observed the refloating process from the water, has scheduled a press conference for Monday afternoon to discuss ongoing cleanup and recovery efforts.
The Dali experienced two electrical blackouts within about 10 hours before leaving the Port of Baltimore on its way to Sri Lanka, according to a preliminary report released last week by the National Transportation Safety Board. The ship experienced two more blackouts as it was approaching the Key Bridge. Those failures caused it to lose propulsion and veer off course at the exact wrong time.
The FBI also launched a criminal investigation into the circumstances leading up to the crash.
The ship’s crew members haven’t been allowed to leave the vessel since the disaster. Officials said they’ve been busy maintaining the ship and assisting investigators. Of the crew members, 20 are from India and one is Sri Lankan.
Officials have said they will be able to disembark once the Dali is docked in Baltimore.
The bodies of six construction workers have been recovered from the underwater wreckage in recent weeks. All the victims were Latino immigrants who came to the U.S. for job opportunities. They were filling potholes on an overnight shift when the bridge was destroyed.
Officials plan to reopen the port’s 50-foot (15-meter) deep draft channel by the end of May. Until then, crews have established a temporary channel that’s slightly shallower.
MAY 2, 2024:
ANNAPOLIS, Md. (AP) — A Maryland transportation official says the state plans to rebuild the Francis Scott Key Bridge in just over four years at an estimated cost between $1.7 billion and $1.9 billion. Transportation department spokesman David Broughton said Thursday (May 2, 2024) the state plans to build a new span by fall of 2028. As salvage efforts continue, authorities also announced late Wednesday they had recovered the body of a fifth person who died in the March 26, 2024, collapse. Meanwhile, the broker for the bridge’s insurance policy confirmed Thursday that a $350 million payout will be made to the state of Maryland.
APRIL 25, 2024:
BALTIMORE (AP) — The first cargo ship passed through a newly opened deep-water channel in Baltimore on Thursday (April 25, 2024) after being stuck in the harbor since the Francis Scott Key Bridge collapsed four weeks ago, halting most maritime traffic through the city’s port.
The Balsa 94, a bulk carrier sailing under a Panama flag, passed through the new 35-foot (12-meter) channel headed for St. John, Canada.
Its voyage marked an important step in the ongoing cleanup and recovery effort as salvage crews have been working around the clock to clear thousands of tons of mangled steel and concrete from the entrance to Baltimore’s harbor.
The ship is one of five stranded vessels expected to pass through the new, temporary channel, including one loaded car carrier. Other ships are scheduled to enter the port, which normally processes more cars and farm equipment than any other in the country.
On Thursday morning, the vessel moved through the channel guided by two tug boats, one in front and one behind. It passed in between red and green buoys marking the channel’s boundaries and glided slowly by the wreckage of the bridge and the grounded Dali, the massive container ship that caused the collapse when it slammed into one of the bridge’s support columns.
Pieces of the fallen bridge are still blocking other parts of the port’s main channel, which has a controlling depth of 50 feet (15 meters), enough to accommodate some of the largest cargo and cruise ships. Officials have prioritized opening a temporary channel deep enough for large commercial vessels to pass through in hopes of easing the economic impacts of the collapse.
The Balsa 94 is expected to arrive in Canada on Monday.
The Dali lost power and veered off course shortly after leaving the Port of Baltimore bound for Sri Lanka last month. Six members of a roadwork crew — all Latino immigrants from Mexico, Guatemala, El Salvador and Honduras — plunged to their deaths in the collapse. Four bodies have been recovered from the underwater wreckage while two remain missing.
A memorial for the victims near the south end of the bridge has grown in recent weeks. It now includes six large wooden crosses decorated with flags from the victims’ home countries and other personal items, including the hardhats and work boots that allowed them to provide for their families and chase the American dream. A painted canvas backdrop displays abstract scenes from the bridge collapse and salvage efforts as well as handwritten notes from the men’s loved ones.
“We want to send a message to the world that we’re here and we care,” said the artist, Roberto Marquez, who was visiting the memorial late Thursday morning. “We will be here working until they are all recovered.”
The new channel will remain open until Monday or Tuesday. It will close again until roughly May 10 while crews work to remove steel from the Dali and refloat the ship, which will then be guided back into the port, officials said earlier this week.
The 35-foot depth is a substantial increase over the three other temporary channels established in recent weeks. It puts the cleanup effort slightly ahead of schedule, as officials previously said they hoped to open a channel of that depth by the end of April.
The port’s main channel is set to reopen next month after the ship has been removed. That will essentially restore marine traffic to normal.
In a court filing Monday, Baltimore’s mayor and city council called for the Dali’s owner and manager to be held fully liable for the bridge collapse, which they said could be devastating for the regional economy. They said the port, which was established before the nation’s founding, has long been an economic driver for Baltimore and the surrounding area. Losing the bridge itself has also disrupted a major east coast trucking route.
Officials have established a slew of assistance programs for port workers and others whose jobs are suffering as a result of the collapse.
The filing came in response to an earlier petition on behalf of the two companies asking a court to cap their liability under a pre-Civil War provision of an 1851 maritime law — a routine procedure for such cases. A federal court in Maryland will ultimately decide who’s responsible and how much they owe.
In the meantime, both the FBI and the National Transportation Safety Board are conducting probes to determine what caused the ship to lose power and strike the bridge.
APRIL 16, 2024:
SPARROWS POINT, Md. (AP) — Nearly three weeks since Baltimore’s Francis Scott Key Bridge collapsed under the impact of a wayward cargo ship, crews are using the largest crane on the Eastern Seaboard to haul the wreckage to a nearby salvage yard.
The heaviest section so far weighed about 450 tons (408 metric tons). In the salvage yard Monday morning (April 15, 2024), workers disassembled the metal trusses by attacking them with propane torches and a pair of giant shears that sliced them into more manageable pieces. Rising from the water nearby was the Chesapeake 1000, a floating crane with a storied history that includes helping the CIA retrieve part of a sunken Soviet submarine.
The Key Bridge took five years to construct in the 1970s. Now, it’s a race against the clock to dismantle the remnants of a fallen Baltimore landmark.
On March 26, six construction workers plunged to their deaths in the collapse. Four bodies have since been recovered.
Salvage crews are hoping to recover the two remaining bodies once more of the debris has been removed. They’re also working toward their goal of opening a temporary channel later this month that would allow more commercial traffic to resume through the Port of Baltimore, which has remained largely closed since the March 26 collapse. Officials plan to reopen the port’s main channel by the end of May.
So far, over 1,000 tons (907 metric tons) of steel have been removed from the waterway. But the work is tedious, dangerous and incredibly complex, leaders of the operation said Monday during a visit to the salvage yard at Tradepoint Atlantic, the only maritime shipping terminal currently operating in the Port of Baltimore.
The facility, which occupies the site of a former Bethlehem Steel plant northeast of Baltimore, has ramped up operations to accommodate some of the ships originally scheduled to dock at the port’s other terminals.
Before removing any pieces of the bridge, divers are tasked with surveying the murky underwater wreckage and assessing how to safely extract the various parts. Coming up with a roadmap is among the biggest challenges, said Robyn Bianchi, an assistant salvage master on the project.
“There’s a lot of debris, there’s rebar, there’s concrete,” she said. “We don’t know what dangers are down there, so we have to be very methodical and slow with that.”
At the same time, crews are working to remove some containers from the cargo ship Dali before lifting steel spans off its bow and refloating the vessel.
“It presents a dynamic hazard,” said Joseph Farrell, CEO of Resolve Marine, which is working on refloating the ship. He said once that happens, the Dali will return to the Port of Baltimore. “Getting it out of there is a priority.”
APRIL 15, 2024:
Extended version:
APRIL 8, 2024:
BALTIMORE (AP) — Salvage crews have begun removing containers from the deck of the cargo ship that crashed into and collapsed the Francis Scott Key Bridge in Baltimore, an important step toward the full reopening of one of the nation’s main shipping lanes. Officials said Sunday (April 7, 2024) that the removal of the containers from the deck of the Dali would continue this week as weather permits. Crews are progressing toward removing sections of the bridge that lie across the ship’s bow to eventually allow it to move. The Dali has been trapped under mangled steel in the Patapsco River since it slammed into the bridge on March 26, killing six workers.
APRIL 3, 2024:
BALTIMORE (AP) — In the moments before the cargo ship Dali rammed into the Francis Scott Key Bridge and sent it crumbling into the water (March 26, 2024), a flurry of urgent warnings crackled over radios and enabled police to block traffic from getting on the span, likely saving lives. But those warnings seemingly didn’t reach the six construction workers who were killed in last week’s collapse of the Baltimore bridge. Their deaths have raised questions about whether the construction company took proper precautions, including keeping a safety boat nearby that might have been able to warn them at least a few seconds before impact.
APRIL 2, 2024:
BALTIMORE (AP) — A tugboat pushing a fuel barge has become the first vessel to use an alternate channel to bypass the wreckage of Baltimore’s collapsed Francis Scott Key Bridge. The disaster had blocked traffic along the vital port’s main shipping channel. Officials say the barge supplying jet fuel to the Department of Defense left late Monday (April 1, 2024) and was destined for Delaware’s Dover Air Force Base. Some barges and tugs that have been stuck in the Port of Baltimore since the collapse are also scheduled to pass through the channel. Officials say they’re working on a second channel that will allow for deeper draft vessels but didn’t say when that might open.
MARCH 29, 2024:
ANNAPOLIS, Md. (AP) — Experts say rebuilding Baltimore’s Francis Scott Key Bridge could take anywhere from 18 months to several years. They also say the cost could be at least $400 million — or twice that much. It all depends on factors that are still mostly unknown. They range from the bridge’s design to the abilities of government officials to swiftly navigate bureaucracy. Ben Schafer is an engineering professor at Johns Hopkins University. He said the project could take five to seven years given all that’s required. The Key Bridge collapsed Tuesday (March 26, 2024) after a cargo ship plowed into it. Officials are scrambling to clean up and rebuild.
MARCH 28, 2024:
Extended version:
MARCH 27, 2024:
Extended version:
MARCH 26, 2024, UPDATE:
BALTIMORE (AP) — Inspectors in June found a problem with the machinery of the ship that caused a major bridge to collapse in Baltimore early Tuesday (March 26, 2024). But according to the shipping information system Equasis, a more recent examination of the ship, called the Dali, didn’t identify any deficiencies. The Dali has been inspected at least 27 times at ports around the world since it was built in 2015. An inspection at a port in Chile in June identified a problem with the ship’s “propulsion and auxiliary machinery.” The most recent inspection listed for the Dali was conducted by the U.S. Coast Guard in New York on Sept. 13, 2023. According to the Equasis data, the “standard examination” didn’t identify any deficiencies.
MARCH 26, 2024, UPDATE:
BALTIMORE (AP) — A container ship lost power and rammed into a major bridge in Baltimore early Tuesday (March 26, 2024), causing it to snap and plunge into the river below. Several vehicles fell into the chilly waters, and rescuers searched for survivors. The operators of the ship issued a mayday call moments before the crash that took down the Francis Scott Key Bridge, enabling authorities to limit vehicle traffic on the span. That’s according to Maryland’s governor. The ship crashed into one of the bridge’s supports, causing the structure to break apart like a toy. It tumbled into the water in a matter of seconds — a shocking spectacle that was captured on video and posted on social media. The crash happened long before the busy morning commute.
Comments