The South Dakota Department of Transportation says the permanent repairs to the “Singing Bridge” on S.D. Highway 1806 over the Grand River will begin today (July 12, 2021), about a week later than had been planned because of a delay in receiving necessary supplies and equipment.
The bridge will be closed to all traffic. The contractor anticipates having all repairs completed and the bridge reopened to traffic within four weeks from project start date. Travelers will need to use an alternate route during the road closure.
The prime contractor on this $240,771 project is Hollaway Bridge and Culvert, Inc. from Pierre.
For the latest on road and weather conditions, road closures, construction work zones, commercial vehicle restrictions, and traffic incidents, please visit https://sd511.org or dial 511.