Morris, Inc. will be conducting asphalt milling and paving operations on various sections of streets in Pierre beginning today (May 15, 2023). Work is expected to be completed by June 15. Please do not park on the impacted streets between the hours of 7am and 7pm.
Flagging personnel will be in place to direct traffic while activity is taking place on each street.
The following streets are scheduled for asphalt milling and overlay:
Street |
Neltom (Lakeside Lane) |
Lakeside Lane (Neltom-Cul De Sac) |
Lakeside Lane (Neltom-Country Drive) |
Coteau (Missouri-Daktota) |
Seventh (Central-Grand) |
Prospect (Euclid-Sebree) |
Elizabeth (Lakewood-Pleasant) |
Fort (Missouri-Dakota) |
Fort (Island View-Missouri) |
Woodriver Quay (Lakewood- Cul De Sac) |
Filmore (Park-Dakota) |
Govenors Drive (Cabot-Broadway) |
Polk (Wells-Capitol) |
Washington (Capitol-Broadway) |