Work has begun on an $11 million asphalt resurfacing project on US Highway 212 from the city of La Plant to US Highway 83 and on pipe repair work on SD Highway 1804 from the Agar corner north, to mile marker 311.
The South Dakota Department of Transportation says the contractor has begun the pipe repair on SD Highway 1804, which should be completed by the end of May. The pipe work will mainly be located off the road with periodic flaggers used to control traffic when needed.
The cold milling will begin on approximately May 23, 2022, with the asphalt paving commencing approximately June 14, 2022, weather permitting.
During both operations (cold milling and asphalt paving) traffic will be carried through the work zones with the use of flaggers and a pilot car. Motorists can expect delays during these times. The contractor anticipates completing all operations, including the asphalt paving, by the middle of September. The overall project completion date is Nov. 11, 2022.