Work will begin Monday (April 5) on an asphalt resurfacing project on US Highway 14 from three miles east of Blunt to three miles east of Harrold.
The project will include cold milling, asphalt concrete resurfacing, bridge rail upgrade and erosion and pipe repair. The bridge rail upgrade portion of the project will begin on Monday, April 5, 2021, with projected completion by the end of the month. Traffic will be moved through the work zone with the use of stop signs, utilizing alternating “stop and go” traffic.
The cold milling will begin May 17, with asphalt paving commencing May 26. During both processes, traffic will be moved through the work zones with the use of flaggers and a pilot car, so motorists should expect delays. The contractor anticipates completing all operations by mid-July.
The completion date for the entire $3.6 million project is Aug. 27, 2021.
For updated road construction information, visit https://sd511.org or dial 511.