SEPTEMBER 9, 2022:
Work continues on a Hughes County bridge on 321st Avenue about 1.5 miles south of Harrold, near the cemetery.
A Hughes County official says the old bridge has been removed and work on the foundations for the new bridge continues. 321st Avenue will remain closed until the replacement structure is in place, which will likely take several months because the contractors are dealing with quite a bit of water in the drainage under the bridge.
Hughes County hopes to reopen the road around Thanksgiving 2022. Motorists should plan to detour around that location until the project is completed.

Courtesy photo.
AUGUST 22, 2022:
Hughes County has contracted to have a bridge replaced on 321st Avenue, about 1.5 miles south of Harrold near the cemetery.
321st Avenue will be closed until the replacement structure is in place. Motorists should detour around that location until the project, which will likely last several months, is completed.






Comments